One of the biggest roadblocks to starting up a data center is getting approval to connect to the electric grid—a wait that could last as long as a decade. Some developers aren't willing to wait and are instead building their own off-grid, or behind-the-meter, gas power plants to fuel the AI boom. xAI's Memphis campus famously used dozens of natural gas turbines, some without permits, as far back as 2024, and it remains the subject of ongoing legal battles.
But the strategy has since become far more common. As of October 2026, developers have announced plans for more than 100 behind-the-meter gas plants at US facilities, with a combined planned capacity of over 115 gigawatts—more than double California's peak power demand. "The biggest motivator for on-site power right now from data centers is speed," says Musfika Mishi, an associate at Bloomberg NEF.
Behind-the-meter doesn't always mean fully disconnected; some plants are bridges until grid connections arrive. Still, experts like Brendan Pierpont of Energy Innovation warn the shift raises important questions, since new fossil fuel infrastructure could lock in emissions for decades.
Source: MIT Technology Review · Summarized by HeadlinesBriefing